(Revises Bugey 3, Golfech 2 outage restart dates under current outages) Oct 9 (Reuters) – The following table provides information on outages at French utility EDF's nuclear reactors. France has 62,990 megawatts (MW) of nuclear generation capacity provided by 57 reactors, data from power grid operator RTE shows. Reuters estimates that 19,330 MW, or about 31%, of that capacity is offline. That puts online availability at 43,660 MW or about 69%. Please click on the link at the bottom to access the data. CURRENT OUTAGES REACTOR NAME CAPACITY (MW) OUTAGE START EXPECTED RESTART REASON NOGENT 2 1,310 Oct 07, 2025 Oct 10, 2025 Planned outage DAMPIERRE 4 890 Oct 06, 2025 Nov 15, 2025 Planned outage CATTENOM 1 1,300 Oct 04, 2025 Oct 15, 2025 Planned outage CIVAUX 1 1,495 Oct 03, 2025 Nov 15, 2025 Planned outage GRAVGELINES 3 910 Oct 03, 2025 Nov 12, 2025 Planned outage PENLY 1 1,330 Sep 30, 2025 Nov 12, 2025 Planned outage ST LAURENT 2 915 Sep 26, 2025 Nov 08, 2025 Planned outage CHINON 2 905 Sep 12, 2025 Oct 22, 2025 Planned outage CHOOZ 1 1,500 Aug 22, 2025 Nov 25, 2025 Planned outage BELLEVILLE 2 1,310 Aug 22, 2025 Nov 26, 2025 Planned outage 910 Aug Oct 30, Planned BUGEY 3 + 16, 2025 2025 ND outage GRAVELINES 1 910 Jul 11, 2025 Oct 28, 2025 Planned outage FLAMANVILLE 3 1,620 Jun 24, 2025 Oct 17, 2025 Unplanned outage DAMPIERRE 1 890 Jun 27, 2025 Sep 28, 2025 Planned outage CRUAS 1 915 Jun 14, 2025 Dec 01, 2025 Planned outage 1,310 Apr Nov 02, Planned GOLFECH 2 + 18, 2025 2025 ND outage BLAYAIS 4 910 Apr 05, 2025 Oct 16, 2025 Planned outage TOTAL OUTAGES 19,330 PLANNED OUTAGES IN FUTURE 905 Nov Nov 22, Planned CHINON 1 + 22, 2025 2025 outage CHINON 2 905 Nov 29, 2025 Nov 29, 2025 Planned outage TRICASTIN 1 915 Oct 25, 2025 Oct 25, 2025 Planned outage FLAMNAVILLE 1 1,330 Oct 10, 2025 Oct 14, 2025 Planned outage CRUAS 3 915 Oct 11, 2025 Oct 13, 2025 Planned outage FLAMANVILLE 2 1,330 Oct 31, 2025 Jun 17, 2026 Planned outage CHINON 3 905 Dec 06, 2025 Dec 06, 2025 Planned outage BELLEVILLE 1 1,310 Jan 18, 2026 Jan 18, 2026 Planned outage BLAYAIS 3 910 Jan 17, 2026 Apr 13, 2026 Planned outage ST ALBAN 1 1,335 Feb 28, 2026 Jun 05, 2026 Planned outage NOGENT 2 1,310 Apr 04, 2026 May 25, 2026 Planned outage BLAYAIS 2 910 Apr 11, 2026 Jul 03, 2026 Planned outage BLAYAIS 1 910 Apr 30, 2026 May 14, 2026 Planned outage RECENT RESTARTS REACTOR NAME CAPACITY (MW) OUTAGE START RESTART DATE REASON 1,330 Oct Oct 08, PENLY 2 + 08, 2025 2025 Unplanned outage GRAVELINES 5 910 Oct 02, 2025 Oct 07, 2025 Planned outage BLAYAIS 1 910 Oct 05, 2025 Oct 06, 2025 Planned outage CHOOZ 2 1,500 Oct 05, 2025 Oct 05, 2025 Planned outage TRICASTIN 1 915 Oct 04, 2025 Oct 05, 2025 Planned outage TRICASTIN 4 915 Oct 04, 2025 Oct 05, 2025 Planned outage CHINON 1 905 Oct 05, 2025 Oct 05, 2025 Planned outage DAMPIERRE 4 890 Oct 04, 2025 Oct 04, 2025 Planned outage CATTENOM 1 1,300 Oct 03, 2025 Oct 04, 2025 Unplanned outage PENLY 2 1,330 Oct 05, 2025 Oct 05, 2025 Planned outage +: Latest change ND: New date NOTE: Data excludes partial capacity cuts. Data on those can be seen on RTE's website: https://www.services-rte.com/en/view-data-published-by-rte/downtime-of-generation-resources.html (Reporting by Ishaan Arora)
(The article has been published through a syndicated feed. Except for the headline, the content has been published verbatim. Liability lies with original publisher.)